Ofgem heat network quarterly reporting: what small networks must submit

Last checked against Ofgem's published guidance on 30 October 2026. Last updated 30 October 2026. How we check. Not legal advice; see disclaimer and sources.

Heat network suppliers and operators in Great Britain report data to Ofgem every quarter, in the month after each quarter ends (July, October, January and April), and once a year in the April window. Data has to be collected from April 2026. Ofgem says submissions through its digital service open “from Autumn 2026”; as of 30 October 2026 it hasn’t publicly announced the first window. It will accept whatever is available for April–June 2026. Verified — every source is linked in the sections below.

Since 27 January 2026, Ofgem regulates heat networks in Great Britain, including communal heating in blocks of flats. Anyone authorised as a heat network supplier or operator has to give Ofgem regular data about the network under authorisation condition A09, “Provision of Information to the Authority”. Verified: Ofgem regular data reporting guidance, para 1.10.

This guide covers what that means in practice for a small private network: one block, one plant room, a landlord or managing agent recovering the cost from residents.

When are Ofgem heat network returns due?

Ofgem’s guidance (10 March 2026) sets out six tables of data points. Some are quarterly, some annual. The annual ones are submitted in the same window as the Q4 return.

Period Covers Submit between
Q1 1 April – 30 June 1 – 31 July
Q2 1 July – 30 September 1 – 31 October
Q3 1 October – 31 December 1 – 31 January
Q4 + annual 1 January – 31 March (annual: 1 April – 31 March) 1 – 30 April

Verified: guidance Tables 1 and 2. An extension to the last day of the following month can be requested (para 2.5). Organisation-level financial data is the exception: it’s due in the quarter your accounts are signed off, within 10 months of year end (para 2.6).

Each figure is a snapshot on the last day of the period unless the data point says otherwise (para 2.2).

What is in a quarterly return?

For a typical private residential block where the same organisation is supplier and operator, the quarterly return has 18 data points across three areas:

Vulnerability and debt (Table 6) — domestic customers who have met the debt trigger (over £200 outstanding for three months or more after the bill date, and not on a repayment plan), self-disconnections, disconnections for non-payment, customers on repayment plans, reconnections, and meters involuntarily switched to prepayment.

Quality of service (Table 7) — complaints received, split into six categories (back billing, quality of service, customer service, vulnerability/debt/switching, pricing, other), how many were group complaints, how many were referred to the Energy Ombudsman, how many were resolved by the end of the next working day, and how many between then and eight weeks.

Pricing (Table 8) — every standing charge (pence per day), every unit rate (pence per kWh), flat fees (£ per day), connection charges received, other one-off charges, and total charges billed to domestic and to non-domestic customers.

Verified: guidance Tables 6–8, pages 18–23.

What is in the annual return?

Another 23 data points for that same block: customer and meter counts (Table 4), billing frequency and payment methods (Table 5), the Priority Services Register count and bad debt (Table 6), and the annual pricing items (Table 8): what a 6,000 kWh reference customer pays, your pricing method, which costs each charge recovers, fuel type, cost of heat, kWh generated and delivered, revenue and running costs. Plus eight organisation-level finance questions (Table 3) if you are not a council or registered social housing provider.

Who has to report what?

Heat in the service charge still counts

If heat is included in rent or the service charge, Ofgem calls it a “bundled” charge. You still report the number of customers in debt (“the customer numbers in debt should still be provided”), split if you bill some customers separately, and standing charges and flat fees inside a service charge are reported as the heat network element only. Verified: paras 2.21–2.22; Table 6, page 18; Table 8, pages 22–23. See our guide on service charges.

When does heat network reporting start?

Ofgem asks networks to collect data from April 2026. Existing networks can register any time up to 26 January 2027, then submit what they have recorded since April, and Ofgem will accept the data available for April–June 2026. Ofgem says the digital service accepts submissions “from Autumn 2026”, and that it will send a Request for Information to registered networks before the first window and publish further guidance on the process before the first reporting period. As of 30 October 2026 it hasn’t publicly announced that window, and the Request for Information goes only to registered networks. Verified: paras 1.7 and 2.14–2.15, and How to prepare for data reporting.

What to do this month

  1. Start a complaints log with type, date received, date resolved and any Ombudsman referral.
  2. Start a debt log: who is over £200 and for how long, repayment plans, any disconnections.
  3. Write down your tariff, or if heat is in the service charge, how the heat element is worked out.
  4. Find the annual figures: fuel bills, heat meter totals, heat revenue, running costs.
  5. Register on Ofgem’s digital service and join the Energy Ombudsman scheme if you haven’t.

Knowingly or recklessly submitting false or misleading data is prohibited under regulation 62 of the Regulations; if you spot an error after submitting, raise it with Ofgem. Verified: para 2.20.

Which of these apply to your network?

The free checker gives you the list in three minutes, with a collection template. Nothing leaves your browser unless you ask for the template by email.

Related guides

What changed on this page

30 October 2026
Full source re-check. Corrected the annual count: 23 network-level data points plus Table 3's eight organisation-level points (31 in all); the page had said 31 plus eight. The bundled-charges sentence now says only what the guidance says (debt count still provided; standing charges and flat fees as the heat element). The Request for Information is cited to paragraph 1.7.
30 October 2026
Re-checked against Ofgem's updated data reporting page. The first window is no longer described as expected in autumn: Ofgem still says 'from Autumn 2026' but had not announced it publicly by 30 October. Added that Ofgem will publish further guidance on the process before the first reporting period.
16 September 2026
Direct answer added at the top; headings reworded as the questions people ask; Ofgem's 'How to prepare for data reporting' link updated to its new address. No facts, sources or labels changed.
15 September 2026
First published, checked against Ofgem's regular data reporting guidance of 10 March 2026.

Spotted an error? Email [email protected] with the page and the source you're looking at — see how we check and correct our guides.